RCP provided programming services to Vector for the replacement and installation of 33kV sub-transmission lines at the Penrose GXP Substation. The project was coordinated around concurrent Transpower works being undertaken in the same area.

The works involved coordination with Vector and Transpower contractors, both civil and electrical, as well as the careful sequencing of activities to minimise risk and ensure that respective activities did not force unnecessary constraints.

COMPLETED  2016     PROJECT CONTACT  Fraser Robertson